Ongoing Meadowbranch Landfill Updates
26 New wells and 4 horizontals continue to increase vacuum. β 300+ scfm increase pre to post installation.
β
β’ New landfill gas system well pumps purchased November 2022, 7 pumps, installations occurring as weather permits for installation of air and forcemain. β Expected completion January 2023.
β
β’ 26 wells installed all under vacuum, as of Oct. 28, 2022.
β
β’ Leachate Evaporator temporarily demobilized October 13, 2022. Taken offline October 3, 2022.
β
β’ There will be a 3rd party construction crew on-site at Meadow Branch Landfill over the next 2-3 weeks (beginning 09/19/2022) installing/re-drilling approximately 20 landfill gas collection wells.
β
β’ The gas plant increased its capacity in early September through addition of membranes and related items. This allows all gas to be processed through the gas plant. β Flare is therefore turned off and will be operational if the plant is unable to receive all available flow.
β
β’ New landfill gas system well pumps installations as of May 2022, 5 pumps.
β
β’ Horizontal gas well installation scheduled for June 2022.
β
β’ Cell construction to be completed by end of June 2022.
β
β’ New landfill gas system well pumps installation as of 4/29/2022, 8 pumps.
β
β’ New air/forcemain for landfill gas system wells is complete as of 4/27/2022.
β
β’ New flare blower motor installed 4/29/2022.
β
β’ April gas system tuning was completed as of 4/22/2022.
β
β’ Phase 2 (5 acres) expected by end of May 2022.
β
β’ Phase 1 (6 acres) of temp cap geosynthetics is complete as of 4/26/2022.
β
β’ Soil excavation and placement within temporary cap areas is complete, April 2021.
β
β’ Temporary Cap installation started on 4/18/2022. β Trenching in waste may be observed during the installation activities.
β
β’ Evaporator back online after regular maintenance shutdown at 10:20 pm on 3/28/2022. β Will be at minimum rates until 8 am, then increasing.
β
β’ Evaporator planned shutdown occurred at 4:00am on 3/28/2022
β
β’ Evaporator will be preforming a planned preventative maintenance shutdown on Monday 3/28/2022. Evaporation rates will be reduced started at 11:00pm on 3/27/2022 to get to minimum rates by 4:00am
β
β’ We will be upgrading the gas collection system between the dates of April 17th and May 6th. This includes the addition of approximately 2,400 ft of horizontal collection pipe and 5 to 6 horizontal well collection points to the gas collection system.